2025

Assembly and construction of masts

400 kV (2025) – realized volume 523 694 kg (complete assembly and construction)

2025

Assembly and construction of masts

100 kV in Slovakia – 360,000 kg of steel structures installed.

2025

Pulling OPGW

Pulling of optical ground wire (OPGW) on the BEM-CHEM / BorsodChem section with a length of 19,061 m – complete work including installation of accessories and coordination with other activities on the route.

Year 2021 

  • 1 × 400 kV Martonvásár (re-routing of the line over the highway) – relocation of conductors and earth wire (EW) to the newly established line. 
  • Veszprém 2 × 100 kV – line re-routing and replacement of conductors with a total length of 3.2 km (assembly and disassembly of towers, phase conductors, and combined earth wire). 
  • Veszprém 1 × 100 kV – insertion of towers into the line. 

 

Year 2022 

  • Substation Reconstruction – implementation of lead-in and modification of lines (2 × 400 kV, Slovenia). 
  • Conductor Replacement and Re-insulation of 400 kV Line – conductor replacement and installation of spacers. 
  • Assembly and Construction of Towers 2 × 100 kV – 230,000 kg. 

 

Year 2023 

  • Conductor Replacement and Re-insulation of 400 kV Line in Slovakia – conductor replacement and installation of spacers. 
  • Perkáta – Iváncsa 132 kV – tower assembly with a weight of 146,748 kg. 
  • Assembly and Construction of Towers in the Czech Republic – 282,684 kg. 

 

Year 2024 

  • Project Buj – Nyírjes 132 kV – tower assembly and construction with a total weight of 292,338 kg. 
  • Conductor Replacement and Re-insulation of 400 kV Line in Slovakia – conductor replacement and installation of spacers. 
  • Buj – Nyírjes – stringing of conductors (2 × 132 kV) and OPGW on a 26-tower section with a total length of 7,602 meters. 

 

Year 2025 

  • Assembly and Construction of 110 kV Towers in Slovakia – implemented volume of 360,000 kg of steel structures. 
  • Assembly and Construction of 400 kV Towers – implemented volume of 523,694 kg (complete assembly and construction). 
  • Assembly of 400 kV Towers – implemented volume of 251,391 kg. 
  • Stringing of Optical Ground Wire (OPGW) on the BEM-CHEM / BorsodChem section – length of 19,061 m; complete works including installation of accessories and coordination with other activities along the route.